đź§ Decision Explainability
Click any order to see exactly why AI made each scheduling decision
Select an order to explain:
ORD-4521 (VIP Corp)
ORD-4522 (Acme Glass)
ORD-4523 (BuildRight)
ORD-4524 (GlassTech)
ORD-4525 (ModernHome)
VC
Order ORD-4521 • VIP Corp International
50,000 pcs • PROD-C089 Clear Float • Due: Feb 9
→ Line 3
Scheduled: Feb 7, 06:00
1
Which production lines can make PROD-C089?
Lines 1, 3, 5, 8 are capable (based on product-line mapping)
2
Which lines have available capacity?
Lines 3 and 8 have slots before deadline (Line 1 booked, Line 5 maintenance)
Line 1: 98% booked until Feb 10 • Line 5: Scheduled maintenance Feb 7-8
3
How long will production take?
32 hours at Line 3 speed (1,562 pcs/hr) vs 38 hours at Line 8
4
Does this meet minimum campaign duration?
Yes - 32 hours exceeds 5-day minimum for this product family
5
What is the color sequencing impact?
Clear Float follows Light Green on Line 3 = 45 min changeover (optimal)
Alternative: Line 8 would require Dark→Clear = 2.5 hr deep cleaning
6
Is this customer VIP?
Yes - Tier 1 VIP, automatically prioritized in scheduling window
🔍 Alternatives Considered
847,291 schedules evaluated
âś“ SELECTED
Line 3, Feb 7 06:00
Optimal color sequence, fastest completion, VIP priority honored, lowest
changeover cost.
âś— REJECTED
Line 8, Feb 7 14:00
2.5 hr extra changeover (dark→clear), 6 hour later start would risk
deadline buffer.
âś— REJECTED
Line 1, Feb 10 06:00
Delivery deadline violated - would arrive Feb 11, failing VIP SLA
requirement.
AI RECOMMENDATION
Schedule on Line 3 @ Feb 7, 06:00
Confidence
98%
Why this decision?
- Line 3 compatible with product thickness specs (validated)
- Optimal sequence: Follows Light Green run, reducing changeover by 45 mins
- VIP Priority met: Delivers 14 hours before deadline (Feb 9)