Overall Progress
67%
2 days ahead
Active Phase
MEP
Day 12 of 30
At-Risk Tasks
3
weather dependent
Est. Completion
May 15
on schedule
Site Prep & Foundation
Jan 5 - Jan 28
Complete
24 tasks 100%
Structural Frame
Jan 29 - Feb 14
Complete
38 tasks 100%
MEP Systems
Feb 15 - Mar 16
In Progress
45 tasks 42%
Interior Finishing
Mar 17 - May 15
Upcoming
62 tasks 0%

Project Timeline

Foundation
Structural
MEP
Finishing
Jan 5 Today (Feb 7) May 15

Upcoming Milestones

Critical Path
Milestone Phase Target Date Days Left Status
HVAC Rough-In Complete MEP Systems Feb 18 11 days On Track
Electrical Panel Installation MEP Systems Feb 24 17 days On Track
Plumbing Pressure Test MEP Systems Mar 2 23 days At Risk
Fire Suppression Install MEP Systems Mar 10 31 days Scheduled
MEP Inspection MEP Systems Mar 16 37 days Scheduled